Carmel Lagoon Ecosystem Protective Barrier and Scenic Road Protective Barrier Systems

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option
   
File number (s): REF120051
Location:
(Vicinity Map:)

Carmel River State Beach

Scenic Road/Carmello Street, Carmel
Assessor's Parcel Number (s): 009-472-001-000; 009-481-004-000; 009-491-001-000
Planning Area: Carmel Area
Project Lead: Shandy Carroll, Management Analyst III, (831) 784-5643, CarrollS@countyofmonterey.gov.
Current Status: Carmel Lagoon Final EIR
Environmental Status: Pending certification and approval of a Project in Public Hearing September 10, 2024
Project Description:

The FEIR proposes implementing three project components: 1) EPB, 2) SRPS, and 3) ISMP with the objective of implementing a solution to improve the functions and values of the ecosystem in and around the Lagoon by restoring the Lagoon’s historic hydrologic, pre-management conditions to the extent feasible to protect and improve habitat for fish and wildlife while maintaining flood protection.

The Board of Supervisors will consider approving the Environmentally Preferred Alternative Project titled SRPS and Sandbar Management Plan (No EPB) and further described in Alternative 5.3.3.2, with Alternative 5.3.2.5 component SRPS described in the EIR as the Mid-Slope Wall and consider recommending staff further explore a home elevation program described in Alternative 5.3.2.3.

Permits: 

Agency:

Documents:

Status:

US Army Corps of Engineers

Part 1 – Background

Part 2 – Pilot Channel diagrams

Part 3 – Channel closure diagrams

Part 4 – Biological Opinion from US Fish and Wildlife Service

Part 5 – NOAA NMFS Concurrence letter

Part 6 – Ca Water Boards Clean Water Act Certification

In effect 2020 - 2025

CA Department of Fish and Wildlife

Lake and Streambed Alteration

OP Law Agreement EPIMS-MON-41445-R4

CA Central Coast Regional Water Quality Control Board

Clean Water Act Section 401 Water Quality Certification

Sixth Amendment – 2023

In effect until October 31, 2024

CA Coastal Commission

Emergency Coastal Development Permit

In effect 29 November 2023 – 29 November 2024

Key Resources:

 
 

Carmel Lagoon Water Levels

Current and forecasted flow at Robles Del Rio Bridge, Carmel River

Wave height at Carmel River Beach

Key Dates:

 

  • 02/02/2024 - 03/20/2024 Public Review period for the 2024 RDEIR
  • 03/10/2023 Agency and Stakeholder Technical Study Meeting on Interim EPB on Property Line Drainage Analysis
  • 07/28/2022 Carmel Lagoon Stakeholder/Agency Meeting Technical Study and update meeting
  • 03/03/2022 Carmel Lagoon Stakeholder/Agency Meeting Technical Study and update meeting
  • 10/20/2021 Winter Preparedness and EIR update meeting
  • 6/2/2021 Technical Studies meeting with Community
  • 5/27/2021 Technical Studies meeting with Agencies, Stakeholders and Technical Advisory Committee meeting
  • 10/19/2020 Winter Preparedness and EIR update meeting
  • 12/02/16 – 1/31/17, Public Review Period for Draft DEIR